Home in Colonia de los Rosales

In progress

Location
Colonia de los Rosales, Madrid
Category
Refurbishments
Architect
Cayetana A. Pérez Delgado
Home in Colonia de los Rosales, under construction — Interior courtyard seen from below, with the façades shored with orange beams and a yellow panel under the sky.

The intervention in this home in Colonia de Los Rosales, in Madrid, is conditioned by the heritage protection of its façade. To preserve it and, at the same time, gain living space, the project plans to lower the ground level by excavating beneath the existing building. This work requires major shoring, stabilisation and structural reinforcement.

Controlled interior demolition

Once the building is stabilised, the interior elements provided for in the project are removed in a controlled way, keeping the necessary shoring. The temporary structure allows work inside without losing support for the elements that must be kept.

Home in Colonia de los Rosales, under construction — Emptied interior with green props, an orange beam and rubble on the floor.
Home in Colonia de los Rosales, under construction — Roof and structure of the house being demolished, with orange shoring beams under the sky.

Shoring and stabilisation

Before the controlled demolition of the interior, a system of shoring, propping and auxiliary stabilisation structures is put in place. These elements keep the walls and the other parts of the building that must be kept stable through the different phases of the work.

Home in Colonia de los Rosales, under construction — Orange shoring beam and steel profiles next to the brick façade.
Home in Colonia de los Rosales, under construction — Interior courtyard seen from below, with the façades shored with orange beams and a person at the back.
Home in Colonia de los Rosales, under construction — Upward view of the courtyard between red shoring beams.
Views after the demolition showing the stabilisation system.

Excavation beneath the building

Lowering the ground level gains living space beneath the existing building. The excavation must be coordinated with the containment and reinforcement work to keep the walls stable.

Home in Colonia de los Rosales, under construction — The excavator beside the exposed ground under the shored façade.
Home in Colonia de los Rosales, under construction — Steel beam holding up the façade wall over the excavation, with a shovel leaning against it.
Home in Colonia de los Rosales, under construction — Two workers in blue helmets in an excavated pit beside a concrete wall.
Home in Colonia de los Rosales, under construction — Excavated pit beside a concrete pillar, with a ladder and steel reinforcement at the back.

Foundation reinforcement

Work beneath the walls is carried out progressively, through localised excavations and the successive execution of reinforcement and containment elements. The steel reinforcement cage documents one of the phases of execution of the new structural elements.

Home in Colonia de los Rosales, under construction — Steel reinforcement in a deep excavation, with perforated formwork at the back.